09 December,2024 10:37 AM IST | Mumbai | Rajendra B. Aklekar
File Pic
The Mumbai Metro Rail Corporation Limited (MMRCL) on Sunday announced that it had completed track laying from Aarey to Cuffe Parade (up line & down line) 100% on the Mumbai Metro Aqua Line 3 corridor. This marks a significant milestone in the project progress towards full commissioning, expected in May 2025.
The first phase of the Mumbai Metro Rail Corporation (MMRC) Line 3, also known as the Aqua Line, was inaugurated by Prime Minister Narendra Modi on October 5 2024 and commercial operations began at 11 am on October 7, 2024. The 12.69 km stretch runs from Bandra-Kurla Complex (BKC) to Aarey.
The first day of full operations for the Aqua Line saw 20,482 passengers between 6:30 AM and 9 PM. The first Sunday after commercial operations began saw the highest single-day ridership of 27,108. In the first month of operation, the Aqua Line saw over 600,000 riders, with an average daily ridership of around 20,000.
Phase 2 of the line, which runs from BKC to Acharya Atre Chowk in Worli, is expected to open in May 2025.
ALSO READ
Warm pause in cold spell ahead
Mumbai to launch unified ticketing system ‘Mitra’ for seamless multimodal travel
Revised Navi Mumbai metro rail line timetable to come into force from Jan 20
Revised Navi Mumbai metro rail line timetable to come into force from Jan 20: CIDCO
MMRCL allots 1.3-lakh sq ft commercial space across 27 Mumbai Metro-3 stations
Following commuter feedback, the Aqua Line 3 also opened a new pedestrian crossing across the Jogeshwari Vikhroli Link Road (JVLR) for the AareyJVLR station commuters. "The Aqua Line 3 has constructed a pedestrian blinker signal along with cat eyes and rumbler strips to give way to pedestrians," an official said.
Phase One- Total Ridership 11,97,522
No. of Trips Scheduled- 13,504
No. of Trips Run in Actual- 13,480
Average Punctuality- 99.61%
No. of Trips Delayed- 0.37% (51)
No. of Trips Cancelled- 0.17% (24)