Home > Mumbai > Mumbai News > Article > MRVC launches 22 girders in Kalyan Badlapur section

MRVC launches 22 girders in Kalyan-Badlapur section

Updated on: 23 December,2024 07:32 AM IST  |  Mumbai
Rajendra B. Aklekar | [email protected]

At Neral, a 110-ton capacity crane was employed, with 23 workers and officials contributing to the smooth execution of the task,” the MRVC spokesperson added

MRVC launches 22 girders in Kalyan-Badlapur section

Workers install girders, overhead wires on the Central Line. Pic/Rajendra B. Aklekar

Listen to this article
MRVC launches 22 girders in Kalyan-Badlapur section
x
00:00

In what will expedite project work and help commuters beyond Kalyan, the work of new infra projects and that of a new rail corridor between Kalyan and Badlapur took a big leap in a period of two hours 25 minutes on the intervening nights of Saturday and Sunday with the launch of 22 girders for multiple projects, a record of sorts.


While 22 girders were launched by the Mumbai Railway Vikas Corporation (MRVC) as a part of the Kalyan-Badlapur additional corridor project, the CR team also launched all sets of girders of the Patri Pul in a period of three hours 20 minutes, replaced turnouts, and overhead wires, and completed a host of other works.


“This is a commendable feat of engineering and teamwork,” an MRVC spokesperson said.


“During the block period, 11 girders were launched at Ulhasnagar. Additionally, nine more girders were launched post-block period at a location away from the railway line, which did not require a block. This resulted in the successful launch of 20 girders at Ulhasnagar in a single night, contributing to a total of 31 girders launched by MRVC in the Kalyan-Badlapur section and at Neral. 

At Neral, a 110-ton capacity crane was employed, with 23 workers and officials contributing to the smooth execution of the task,” the MRVC spokesperson added.

Kalyan-Badlapur project update
. Sanctioned cost Rs 1,510 crore
. Progress: 26%
. Executing Agency: MRVC
. Land Acquisition: Private land (Pvt. land revenue 6.59 hectares, Pvt. land MIDC 3.18 hectares = 9.77 ha. Total 9.77 ha of private land has been acquired.
. Government land (2.59 ha): Entire government land required for the project has been acquired.
. Forest land (0.25 ha): Stage I clearance received. Working permission received.

"Exciting news! Mid-day is now on WhatsApp Channels Subscribe today by clicking the link and stay updated with the latest news!" Click here!

Register for FREE
to continue reading !

This is not a paywall.
However, your registration helps us understand your preferences better and enables us to provide insightful and credible journalism for all our readers.

Mid-Day Web Stories

Mid-Day Web Stories

This website uses cookie or similar technologies, to enhance your browsing experience and provide personalised recommendations. By continuing to use our website, you agree to our Privacy Policy and Cookie Policy. OK